A2-039 - Here We Are Story (1999)
Post Feasibility June 1998 to September 1999 stage 6th September 1999 steering group, more of the same, funding, building planners. Document in archive cupboard.
Post Feasibility June 1998 to September 1999 stage 6th September 1999 steering group, more of the same, funding, building planners. Document in archive cupboard.
Autumn 1999 – Autumn 2000, largely the building and the junction. 21st October 1999 minutes of meeting. The good news, we had been granted £50k… Read More »A3-002 – Here We Are Story (1999)
Autumn 1999 – Autumn 2000, largely the building and the junction. 23rd November 1999 minutes of Steering Group meeting. Covering building gone out to tender,… Read More »A3-004-001 – Here We Are Story (1999)
Autumn 1999 – Autumn 2000, largely the building and the junction. 12th January 2000 meeting notes Re the building three contractors have been asked to… Read More »A3-010 – Here We Are Story (2000)
Autumn 1999 – Autumn 2000, largely the building and the junction. 10th February 2000 Steering Group meeting notes. All tenders received are well over budget… Read More »A3-017 – Here We Are Story (2000)
Flyers on how Here We Are begun and what we have done.
David Sumsion, John MacDonald, Jackie MacPherson, Christina Noble, Alice Beattie and Alistair MacCallum
Scottish Heritage Angel Award 2015 and Civic Champion Award 2016
Gazetteer 17th July – 8th August, by Ali Campbell 2012 The Gazetteer Project is about how the land has changed from the 1900’s to 2012.… Read More »GAZ1-017-001 – Gazetteer of Cairndow (2012)
I had 4 weeks working at Here We Are on “A Gazetteer of Cairndow” project from 16th July – 08th August 2012. It is about… Read More »GAZ1-018-001 – Gazetteer of Cairndow (2012)