Autumn 1999 – Autumn 2000, largely the building and the junction.
10th February 2000 Steering Group meeting notes.
All tenders received are well over budget – which is £115k. David Sumsion says he and the QS thought they would come in around £140 – 50 but they are at £180. Lizzie explains that the money we have is the money we have – there is no more. Gordon MacLeod the QS said he apologised he hadn’t realised the complexity of the building and he did not charge additional fees for re-doing the drawings/calculations. David Sumsion says his fees were at risk and he will charge for the re-tender. Document in archive cupboard.